- Project No. 008-14 “Modernization of the Corrosion Chamber of GX3 and GX4 Units”, December 2014.
- Client: TCO (Tengizchevroil)
- Project Objective: Replacement of sulfur granulation unit equipment for GX3 and GX4 chambers.
- Location: TCO Plant, Unit 600.
- Process Equipment Supplier: Enersul, Canada.
- Engineering disciplines involved: Piping and Mechanical Engineering, Building and Structural Design, Electrical Engineering, Instrumentation and Control (I&C).
- Piping and Mechanical: 80 drawings + 2 documents + documentation package
- Building and Structural Design: 10 drawings + 3 calculation documents + documentation package
- Electrical: 5 drawings + 1 document + documentation package
- I&C: 31 drawings + 5 documents + 51 technical data sheets + documentation package.
Project Constraints and Challenges:
- Limited space at the work site;
- Partial absence of original drawings in the TCO database and archives, requiring redevelopment of missing documentation;
- Hazardous area due to high H₂S concentration, requiring detailed consideration within contractor documentation packages;
- At TCO’s initiative, the project was suspended four times, with a total suspension period of 697 days;
- CO revised the project scope three times; despite significant changes to the execution strategy, all documentation packages were fully updated and delivered within tight deadlines.