Modernization of the Corrosion Chamber of GX3 and GX4 Units

  • Project No. 008-14 “Modernization of the Corrosion Chamber of GX3 and GX4 Units”, December 2014.
  • Client: TCO (Tengizchevroil)
  • Project Objective: Replacement of sulfur granulation unit equipment for GX3 and GX4 chambers.
  • Location: TCO Plant, Unit 600.
  • Process Equipment Supplier: Enersul, Canada.
  • Engineering disciplines involved: Piping and Mechanical Engineering, Building and Structural Design, Electrical Engineering, Instrumentation and Control (I&C).
  • Piping and Mechanical: 80 drawings + 2 documents + documentation package
  • Building and Structural Design: 10 drawings + 3 calculation documents + documentation package
  • Electrical: 5 drawings + 1 document + documentation package
  • I&C: 31 drawings + 5 documents + 51 technical data sheets + documentation package.

Project Constraints and Challenges:

  • Limited space at the work site;
  • Partial absence of original drawings in the TCO database and archives, requiring redevelopment of missing documentation;
  • Hazardous area due to high H₂S concentration, requiring detailed consideration within contractor documentation packages;
  • At TCO’s initiative, the project was suspended four times, with a total suspension period of 697 days;
  • CO revised the project scope three times; despite significant changes to the execution strategy, all documentation packages were fully updated and delivered within tight deadlines.